What are the requirements for installing lightning arresters?

Apr 21, 2020

Ostavi poruku

(1) First fix the base of the arrester, and then install the units (sections) of the arrester step by step from bottom to top.


(2) The lightning arrester has passed the assembly test and passed before leaving the factory. The on-site installation should be assembled strictly according to the manufacturer's number, and cannot be interchanged, so as not to change the characteristics.


(3) Valve type arresters with series and parallel resistors should be selected during installation so that the nonlinear coefficients of the same-phase combined units are close to each other, and the difference should not be greater than 0.04.


(4) The contact surface of the arrester should be wiped clean, the oxide film and paint should be removed, and a layer of power compound grease should be applied.


(5) The lightning arrester should be installed vertically with a sag deviation of not more than 2%. If necessary, a metal sheet can be calibrated between the flange faces. The three-phase center should be on the same straight line, the nameplate should be on the same side for easy observation, the equalizing ring should be installed horizontally, and finally the gap should be smoothed and painted with putty.


(6) Tighten the insulator string to make it tight. The tension of each string in the same phase should be balanced to avoid the additional stress of the arrester.


(7) The discharge counter should be well sealed, reliable in operation, and the three-phase installation position is consistent for easy observation. The grounding is reliable, and the counter indicates the return to zero.


(8) The exhaust channel of the zinc oxide arrester should be unobstructed, and the exhaust gas should be avoided during installation, causing short circuit between phases or flashover to the ground, and no other equipment should be sprayed.